EPCI Subsea Facility for TSB Phase 2 Development

Client Name : Kangean Energy Indonesia Ltd

Project Period : 6 January 2017 - 5 October 2019

Project Location : 120 km from Pagerungan Island, off the north coast of East Java Indonesia,  130m - 230m Water depth

Project Scope : Development of 4 gas fields – Terang, Sirasun East, Sirasun West and Batur


Infield Pipeline

• 26” Production Flowline from Sirasun Manifold to Terang PLET 23.3km

• 20” Flowline Spool from Terang PLET to Existing Terang Manifold

 

Flexible Pipeline

• 10” Flexible infield flow line from BTO-1 to Batur Tee, approx. 1.3km

• 10” Flexible infield flow line from SIO-01 to Sirasun Manifold, approx. 8.0km

• 12” Flexible infield flow line from SIO-02 to Sirasun Manifold, approx. 1.9km

• 12” Flexible infield flow line from SIO-03 to Sirasun Manifold , approx. 1.6km 


Umbilical

• New Terang UTA to Batur SDU, approx. 9.6km

• Batur SDU to Sirasun SDU, approx. 14.5km

• Batur SDU to BTO-01, approx. 1.3km

• Sirasun SDU to SIO-01, approx. 7.9km

• Sirasun SDU to SIO-02, approx. 1.9km

• Sirasun SDU to SIO-03, approx. 1.5km


Subsea Structures

• Sirasun Manifold (4x28” driven pile)

• Batur In-line Tee (Mudmat)

• Terang PLET (2x28” driven pile)

• Support & Protection Stucture for Sirasun SDU (1 driven pile), Batur SDU (Mudmat) and Terang UTA (Mudmat)

• Spool-pieces for pipeline tie-ins 

Project Overview : Kangean Energy Indonesia Ltd is developing the TSB Project in two phases. Phase 1 was completed by Timas in 2011/2012. 
TSB Phase 2 project consist of 4 offshore gas well for producing gas from Batur (one subsea well) & Sirasun (Three subsea wells) shall be tie back to existing TSB-1 facilities to carry the produced fluids from Phase II facilities.
The four infield flexible flow lines gathered production fluid from 4 subsea wells, of which three are in Sirasun field and one is in Batur field. A production flow line transport the produced fuel from these fields to the FPU Joko Tole via existing Terang Manifold. 

Other Projects
Eastern Hub Mercury Removal (EHMR) Water Project
Eastern Hub Mercury Removal (EHMR) Water Project
KF Gas Booster Compression Project
KF Gas Booster Compression Project
Lima Power And Safety System Upgrade Project
Lima Power And Safety System Upgrade Project
UL Development Project
UL Development Project
Waste Heat Recovery Steam Generator Project
Waste Heat Recovery Steam Generator Project
Design and Fabrication Equipment Module for Minas Surfactant
Design and Fabrication Equipment Module for Minas Surfactant
EPC of Water Tanks Facility in Three Gathering Station
EPC of Water Tanks Facility in Three Gathering Station
Anoa Phase AGX Compression Reconfiguration
Anoa Phase AGX Compression Reconfiguration
Tembang 8 to Bawal Pipeline System Permanent Tie-Ins
Tembang 8 to Bawal Pipeline System Permanent Tie-Ins
Engineering and Installation Services for Jangkar Umbilical Project
Engineering and Installation Services for Jangkar Umbilical Project
Bukit Tua Field Development
Bukit Tua Field Development
Lima Subsidence Remediation Project
Lima Subsidence Remediation Project
Pembangunan Main Oil Line (MOL) Dari Anjungan XA Process Lapangan X-Ray ke Pusat Pengumpul Produksi
Pembangunan Main Oil Line (MOL) Dari Anjungan XA Process Lapangan X-Ray ke Pusat Pengumpul Produksi
Reroute Gas Pipeline L-Parigi-Cilamaya Project
Reroute Gas Pipeline L-Parigi-Cilamaya Project
EPCI Subsea Facility of TSB Field Development Project
EPCI Subsea Facility of TSB Field Development Project
Ujung Pangkah CPP and AUP Platform Installation Contract
Ujung Pangkah CPP and AUP Platform Installation Contract
Pagerungan Utara Offshore Installation for Wellhead Platform Project
Pagerungan Utara Offshore Installation for Wellhead Platform Project
North Belut Pipelines Installation Project
North Belut Pipelines Installation Project
North Belut Installation of Wellhead Platform Project
North Belut Installation of Wellhead Platform Project
Kambuna Offshore Topside, Riser, and Pipeline Installation
Kambuna Offshore Topside, Riser, and Pipeline Installation
CNOOC EPCI MILA-A And ASTI-A Platforms And Pipelines Project
CNOOC EPCI MILA-A And ASTI-A Platforms And Pipelines Project
EPCI Services For Infill Well Facility Tie In KRA SOUTH 2 Project
EPCI Services For Infill Well Facility Tie In KRA SOUTH 2 Project
EPCIC Of The Pipeline System For Lampung LNG Floating Storage Regasification Facilities
EPCIC Of The Pipeline System For Lampung LNG Floating Storage Regasification Facilities
TOTAL E&P Indonesie Bekapai Phase 2B EPSC2 Project
TOTAL E&P Indonesie Bekapai Phase 2B EPSC2 Project
Provision of Shore Approach Services in Support of the Jangkrik Complex Project
Provision of Shore Approach Services in Support of the Jangkrik Complex Project
KG & KH Riser Replacement Project
KG & KH Riser Replacement Project
KE30 Platform Installation and Subsea Pipeline Laying Project
KE30 Platform Installation and Subsea Pipeline Laying Project
SUBAN COMPRESSION PROJECT
SUBAN COMPRESSION PROJECT
TISSUE MACHINE BLOCK # 11.1 & 11.2 PROJECT
TISSUE MACHINE BLOCK # 11.1 & 11.2 PROJECT
OKI Pulp & Paper Project
OKI Pulp & Paper Project
PENGGANTIAN 1 UNIT SUB STATION
PENGGANTIAN 1 UNIT SUB STATION
CNG Plant Bangkanai
CNG Plant Bangkanai
Viscose ,Spinbath & Spinning Civil Structure & Partition
Viscose ,Spinbath & Spinning Civil Structure & Partition
TREATED DESTILLATED AROMATIC EXTRACT (TDAE) PROJECT
TREATED DESTILLATED AROMATIC EXTRACT (TDAE) PROJECT
Replacement of Grease Plant in Jakarta Lubricants Production Unit of Marketing & Commerce Directorat
Replacement of Grease Plant in Jakarta Lubricants Production Unit of Marketing & Commerce Directorat
SLN Tank Repair and Replacement
SLN Tank Repair and Replacement
NPK Fusion Project
NPK Fusion Project
Engineering, Procurement, Construction and Installation (EPCI) of Subsea facility for TSB Phase 2
Engineering, Procurement, Construction and Installation (EPCI) of Subsea facility for TSB Phase 2
Buntal-5 Project Engineering, Procurement, Construction and Installation (EPCI)
Buntal-5 Project Engineering, Procurement, Construction and Installation (EPCI)
Offshore Pipeline and WHP Installation Services
Offshore Pipeline and WHP Installation Services
Transportation & Installation of Mini Platform
Transportation & Installation of Mini Platform
EPCI Subsea Facility for TSB Phase 2 Development
EPCI Subsea Facility for TSB Phase 2 Development
EPCI Services for the Bison, Iguana and Gajah Puteri (BIGP) Development Project
EPCI Services for the Bison, Iguana and Gajah Puteri (BIGP) Development Project
Construction Work at TDAE Plant Project
Construction Work at TDAE Plant Project
Penggantian Column 011C106 Beserta Accesoriesnya Di Area FOC-II
Penggantian Column 011C106 Beserta Accesoriesnya Di Area FOC-II
EPC for Suban Compression Project
EPC for Suban Compression Project
FL1 Project Mechanical and Piping Works (Package 1A, 2 and 3)
FL1 Project Mechanical and Piping Works (Package 1A, 2 and 3)
Fabrication and Pre Assembling Dew Point Control System And Production Cooler
Fabrication and Pre Assembling Dew Point Control System And Production Cooler
Deareator ID 3800 x 18560 T/T & Tower ID 2700 x 6000 T/T
Deareator ID 3800 x 18560 T/T &  Tower ID 2700 x 6000 T/T
Gajah Baru Project
Gajah Baru Project
MEG Injection Package
MEG Injection Package
Heavy Clad Vessel for Suban Gas Compression Project
Heavy Clad Vessel for Suban Gas Compression Project
Naptha Splitter Column ID. 4,000mm x 12t x 32,330mm
Naptha Splitter Column ID. 4,000mm x 12t x 32,330mm
EPCI Service Contract for: EPCI-1 : PHE-12, PHE-24 and CPP2 Platforms and Pipeline
EPCI Service Contract for: EPCI-1 : PHE-12, PHE-24 and CPP2 Platforms and Pipeline
RDMP Balikpapan Project
RDMP Balikpapan Project